Work Session

September 18, 2021

 

To join the fun, contact the railroad at: Work-Session @ RedRiverAndGulf.net (no spaces)

 

Volunteers
Everett
Angela
Andrew
Glen
Wimbley
Mike M.
Chance
Scott
Tucker

Accomplishments
M4 dashboard wiring traced and installed
Tie replacement on Main Loop
Run herbicide train
Evaluation of operational repairs to wheeled and tracked logging equipment

Thank you to all our volunteers for coming out this weekend! Your efforts are most appreciated, and many months of hard work is going to be enjoyed by many museum visitors at our upcoming fall events.

Before the Weekend
Mike M. has been hard at work over the past few weeks working with the museum staff preparing for upcoming fall events at the museum. New LED lighting has been installed at the Planer Mill, work continues on the new Archives building, and additional lighting has been installed in the Finished Lumber Shed.

At the last volunteer weekend, Glen took the old dashboard out of the M4 to make a new one. The old dashboard and wiring had been added to, changed, added some more, and changed again many times over the years. Glen has made a new, very professional dashboard for the M4. The controls and gauges will be labeled, and it will be a fine upgrade to the M4.

Saturday
Saturday morning began with the group reviewing the donation of several boxes of archive material and photos donated to the museum. The museum archives continue to grow, and we are excited for more material to be catalogued, digitized, and made available for researchers and historians.

After reviewing the many photos of the mill, woods operations, and locomotives, the volunteers split into two groups. Group #1 of Glen, Wimbley, and Mike M. worked on the M4. The electrical wiring was traced and tested for proper operation before the new dashboard is installed. This is tedious and technical work, but we thank and applaud all those doing this work. The plan is to ensure the wiring is in working order and to install a master disconnect to the battery. This will prevent an unneeded draw on the battery when the M4 is not in use and represents a good upgrade to the M4.

Group #2 of Everett, Angela, Andrew, and Tucker set to work replacing ties on the Main Loop. Rain inundated Longleaf for days leading up to the weekend and with more rain forecasted, the rental of a mini excavator was not carried out. However, the weather was indeed decent, and work progressed replacing rotten ties. With a flatcar loaded with tools and Everett operating the tractor, the crew headed out to replace ties on the Main Loop near where the M4 had derailed in May. Everett brought in ties to the work site while Angela, Andrew, and Tucker cleared away pine straw, removed spikes, and began shoveling dirt out to pull out the rotten ties. After much digging and pulling, the rotten ties were removed, and fresh ones put in their place. I must tip my hat to Andrew and Angela, they remembered the spiking lessons from earlier this summer and their spike-driving skills have improved mightily. The fresh ties were spiked down and many of the ties in this area also received new spikes on the outside curves. The rail dynamics in this particular area had pushed out several spikes, but this was corrected today. Riding over this section is significantly improved.

At midday, the crews broke for lunch, courtesy of the museum. Thank you to the museum staff for the lunch! The tractor, unfortunately, broke for lunch too. The hydraulic lines sprung a leak. Everett spent the remainder of the afternoon fetching the needed parts in Alexandria and repaired the tractor back to service by the close of the day. After lunch, work progressed on the M4 wiring work and continued efforts replacing ties in the track. Wimbley came to assist with the tie replacement effort and with luck, the next tie replaced was a piece of cake! Excellent timing Wimbley! After the main work for the day was done, plans were discussed and formulated for future efforts.

Sunday
Chance and Scott, museum visitors of a few weeks ago, came out Sunday morning to inspect and evaluate the wheeled and tracked logging equipment in the finished lumber shed. Chance is well versed in diesel mechanics of these machines and his report and efforts are invaluable in potentially getting these pieces of equipment operating again. The first plan is restoring one of the Allis-Chalmers HD-15 to operation and potentially one of the CAT D7 bulldozers. Thank you to Chance and Scott for these efforts!

Glen, Mike, and Wimbley continued work on the M4 wiring and dashboard installation. Everett, Angela, and Andrew set out to install joint bars on the Main Loop track to ensure curves were smooth to operate over. A herbicide spray was finally conducted over the Sandersville line, with much blow-down tree tops covering the track. Fortunately, these limbs were cleared by hand and spraying was done all the way to the washout. The Main Loop and the wye east leg also received a herbicide spray as well. While the final spraying was ongoing, Everett, Angela, and Andrew removed a rotten tie on the main line track near the engine house at Switch #7 (Switchback Jct). Replacing this rotten two with two fresh ones completed the track maintenance efforts for the weekend.

The M4 is receiving repairs and much needed upgrades. The Main Loop track is getting into much better shape. M4 rides will be coming soon, fall events are around the corner, and the weather will be cooling off soon. Thank you to our volunteers this weekend, and please consider joining us in the near future.

-Tucker Baker
  RR&G Road Master

 

Angela & Andrew

 

Angela, Andrew & Wimbley

 

New tie

 

Tightening bolts

 

Hydraulic leak on the tractor.

Everett was able to find the parts to repair it.

 

The new control panel on the M4 is fantastic!

Glen did an amazing job!

 

Glen working on the M4's engine

 

New horn

 

Glen and the M4

 

<- Angela & Andrew

Workin' on the railroad ->

 

<- The Weed/MOW Train

Tucker joins the fun ->

 

This is hard, but rewarding work.

 

 

The Weed/MOW Train