a

Work Session

February 4, 2023

 

To join the fun, contact the railroad at: Work-Session @ RedRiverAndGulf.net (no spaces)

 

Volunteer Railroaders
Everett L
Jason R
Noah R
Joe S
Gavin R
Dewayne S
Carson S
Clint L
Nick P
Dylan S
Wimbley V
David H
Glen A
Kira S
David S
Ayden S
Toby S
Tyler S
Mike M
Doug R


Accomplishments
1. Competed the Flatcar Rebuilding Project

2. Roadbed for Engine House Track #3 95% Complete

3. Car Shop Outhouse Cleared

4. Car Shop Track Clean-up Completed

5. Progress Made on RR&G M33 (Ford Model T)


Saturday

Due to heavy rains just ending on Thursday night, the decision was made on Saturday morning to postpone repairs and a greater reconstruction of the Grigsby Gulch Bridge. Accordingly, in the morning, the work force split into four groups. Cars were switched around so that the M-8 could take the large work flat down to the location of the former motor car sheds and the remains of Model T car #33. Glen has written a report covering what that group recovered and what they found out that is included in this report later.


Dewayne set about installing trailer type electrical connections for the sprayer car, so that it can be used easily by either the M-2 or the M-8. He completed the M-2 in the morning and the M-8 in the afternoon. He was helped by Ayden and several other volunteers at various times.


David, David and Everett set about gauging the wheels on the partially rebuilt 4 wheel flat car worked on at the last work session. After the wheels were gauged, the Model T crew returned, and the flat car deck was stripped off by Wimbley, Gavin, Ayden, Dylan, Clint, Carson, and Dewayne using sledge hammers to destroy the rotten deck. Nothing that young men like to do better than to take sledge hammers to a job. When the deck was off, and clean up completed, it was discovered that only a single main frame member and a single end were not beginning to rot. So, after lunch, David, David and Everett rebuilt the frame with new timbers, and then the new deck was put on, giving us a new flat car for the next 20 years.


At the same time, Jason got the tractor and started digging down to the depth required to re-lay Track 3 into the Engine House. It was not bad going out side the Engine House, but inside was a different matter. Inside was a packed mess of oil soaked gravel, and cinders, as well as the ties that remained when track three was removed in 1957.

 

Mess-1, Tractor-0

 

Jason and Joe went and got one of the Fresno scrapers to see if they could get it to cut the tough stuff, but no go.

 

Mess-2, Tractor + Scraper – 0.


While this was going on, Jason took a couple of breaks, and took visitors to the museum for a couple of rides on the M-4, with Doug handling the final run of the day.


Several of the volunteers went to the Commissary to help Doug move a large exhibit table as well early in the afternoon.


David H then suggested using the fork lift as a digging tool. With Jason and David running the all terrain lift, the score quickly became:

 

Mess-2, Forklift-1

 

With the first layer torn up, the digging commenced in earnest. Digging up the rotten ties required the intervention of many of the volunteers as all of the wood mess had to be dug out by hand after being ripped up by the forklift.


While the digging was going on, Ayden and Dylan got instruction on the M-8 and with Clint and Carson running the M-2, everything was switched around and put back on Track #1 at the end of the day.
 


Sunday
More digging and dirt moving commenced on the grade for Track #3. David H brought his tractor and box blade so that we were using both the museum tractor and David’s tractor along with the Forklift.


Nick, Ayden, Wimbley, Gavin and Everett finished the clearing of the area cleared by the CCC crew in December, removing the 6-8” tree stumps and such so that it could be more safely entered and enjoyed. They also cleared a path to and an area around the remaining outhouse behind the shop, so that reconstruction on that historic object may be started.

 

The day ended with the Track 3 road bed about 95% complete. At the next Work Session we plan to finish it and then put down ties and rails.


 

-Everett Lueck
  RR&G General
Superintendent

 

Saturday morning safety brief

 

David led the project to finish the flatcar rebuild, including a new deck.

 

Jason used the tractor to being removing soil/ballast to make a roadbed for Engine House Track #3

 

M4 poses on the Loop between runs.

A few passengers got a ride later in the day.

 

Joe operates the grader

 

Under Everett's leadership, Wimbley, Clint, Nick, Carson, Dylan, Dewayne, and Gavin cleared brush and trees from the Car Shop Outhouse.

 

A cosmetic (only) restoration is planned for the future

 

Re-decking the flatcar

 

The floor of the Engine House where Track #3 used to be was covered by a crust as hard as concrete. We used the tractor and the road grader in attempts to break through, but never succeeded in more than a light scrape. As near as we can tell, this crust was comprised of coal clinkers covered by oil drippings and blown-in dust, then compacted by a decade of trucks driving over it.

 

In the photo above, we picked several trenches in order for the road grader to get a bite.

 

Our efforts were not successful.

 

 

 

Placing the road grader in the newly dug trench.

The guys adding their weight to hold the blade down while Jason used the tractor to slowly pull the grader.

 

Jason using the tractor to pull the Fresno scrapper loaded with teenagers for ballast.

 

The soil & ballast outside the Engine House was much easier to move.

 

We had some marginal success with the grader, but it was SLOW going.

Joe is removing material so we could continue. But then...

 

David Hearne had the brilliant idea to use the forklift. He taught Jason how to run it and we had immediate success!

The tines were driven under the crust and then lifted, breaking it up.

 

This is what the forklift accomplished in just 5 minutes!

 

The forklift cab frames the scene as M8 backs into the Engine House with Dylan at the controls while Wimbley runs M2 up the Main Line.

 

A really pretty evening at Long Leaf

 

Dinner at Mama Bear's Cafe in Forest Hill.

The food was really good and we'll definitely be visiting the establishment more often.

 

Sunday morning started off cold and strong coffee was needed.

By noon the temperature had warmed to 70.

 

David brought his tractor and box blade to help clear out debris from the new track bed.

It worked really well!

 

David uses the forklift break up the next layer of crust.

 

Joe takes a turn

 

 

After the forklift broke up the hard stuff, we used the grader again with much more success.

Nick, Joe, & Wimbley. Jason is driving... and taking pictures.

 

About 90% done.

 

We'll do a bit of clean-up grading at the next Work Session, then we'll put down ties.

 

David shows off the newly decked flatcar

 

Ready for service!